|
In 1994 Redfern entered into the Mine Development Assessment Process
(MDAP) in British Columbia to secure approval-in-principle for mine
development. Concurrently the project application was entered into
the federal environmental assessment process at the screening level
under the Canadian Environmental Assessment Act (CEAA). By June
of 1995 the new BC Environmental Assessment Act superseded the MDAP
and the project application was transitioned into the new process
at the Draft Specification stage.
Redfern was granted a Project Approval Certificate (PAC) in March
of 1998 and immediately applied for key operating permits as well
as conducting work to meet conditions imposed by the Certificate.
Most of the effort was dedicated to the Special Use Permit (SUP)
governing the construction and operating approval for the mine access
road. The SUP was obtained in conditional form in 1999 and most
of the conditions were removed in May 2000 pending submission of
final engineering design documents and final construction approval.
In early 1999 a legal challenge to the Project Approval Certificate
was filed by the Taku River Tlingit First Nation (TRTFN), with the
support of environmental organizations opposed to development. In
June of 2000 the BC Supreme Court ruled that the final stages of
the project environmental review had not sufficiently addressed
aboriginal concerns and ordered the PAC quashed. The court subsequently
ordered that the final stage of the review be re-done commencing
in September 2000 for a period of two months. Redfern put the further
development of the Tulsequah project on hold pending a resolution
under the order. Meantime, the BC government and Redfern filed an
appeal of the BC Supreme Court decision.
The formal Project Committee re-consideration process started in
September 2000 but continued past the court’s suggested time
frame in order to more fully explore all issues. In fact, the review
committee were still examining the issues in January 2002 when the
BC Court of Appeal made public its decision. The Appeal Court found
that the earlier Supreme Court decision was in error and that the
original review process had indeed been properly conducted. The
Court further ordered that the re-consideration process be set aside
and that the project instead be remitted back to the ministers to
re-do their decision on a Project Approval Certificate. The rationale
for this centred on the Court’s interpretation of how the
province had dealt with the asserted rights of the TRTFN in its
original decision. Since the Crown had argued that it only considered
established rights, the Court ordered that the Ministers also give
consideration to the potential impacts of the project on asserted
rights in reaching their new decision.
The Ministers were provided with all of the necessary documentation
at the beginning of June 2002. A final decision was made in December
of 2002 and Redfern was awarded a new Project Approval Certificate
for the project.
The Province applied for leave to appeal to the Supreme Court
of Canada concerning that aspect of the BC Court of Appeal decision
requiring the Crown to consider asserted aboriginal rights. Leave
was granted by the Supreme Court on November 14, 2002. A cross-appeal
application by the TRTFN was dismissed. In March 2004 the Supreme
Court of Canada heard the appeal and rendered its decision on November
19, 2004. In this decision the Supreme Court unanimously decreed
that the province of BC had met its obligations, upholding the
adequacy of the provincial consultation and accommodation of the
interests of the Taku River Tlingit First Nation in the environmental
assessment
and certification of the Tulsequah project.
Environmental Assessment
The Environmental Assessment process that reviewed the Tulsequah
project was rigorous and lengthy. All of the project components
were examined in detail. Redfern was required to address a detailed
list of Project Report specifications in completing the environmental
baseline studies and providing design information for the Project
Report, which was the final subject of review. Throughout this process
Redfern engaged in a comprehensive public consultation process including
very intensive consultations with the Taku River Tlingit First Nation.
This was evidenced in the comments of the presiding judges in the
subsequent litigation process where no fault could be found with
Redfern’s consultation record or conduct in completing the
review.
The Project Committee formed to oversee and direct the review of
the Tulsequah project encompassed all of the key jurisdictional
groups. Members of the Project Committee (as struck in 1995) were:
Provincial:
Ministry of Transportation and Highways
Ministry of Energy and Mines
Ministry of Environment Lands and Parks
Ministry of Forests
Ministry of Small Business, Tourism and Culture
Federal:
Environment Canada
Fisheries and Oceans Canada
Coast Guard
Extra-provincial:
Yukon Territorial Government
Municipal:
Atlin Advisory Planning Commission
First Nation:
Taku River Tlingit First Nation
USA:
State of Alaska
US Department of the Interior
US EPA
The multi-faceted Project Report submitted by Redfern in July of
1997 consisted of 5 volumes and 5 appendices in separate volumes.
Most of the work was broadly subdivided into the two key geographical
components of the project: the mine site and associated infrastructure,
and the access road.
It is impossible to summarize here the full scope of the environmental
assessment studies and documentation but a sense of the rigour and
scope of the work can be obtained through a brief examination of
the main study elements for the access road review:
Environmental Assessment and
Special Use Permit (Access Road)
Figure 1 shows the existing access roads in the project Area.
As can be seen there are no roads providing access to the Mine.
In
the north Atlin is served by Highway 7 which provides access to
the Alaska Highway and the continental road network. In the immediate
Atlin area public roads extend a short distance east and south
providing access to residents in these areas and to the Five Mile
reserve
of the Tlingits. A large number of unregulated roads web the area
east and south of Atlin. These roads have been developed over
the
previous century of placer mining operations in the Atlin district
and have been used for recreational purposes by local residents.
At present in excess of 200 kilometers of these roads
traverse the 1000 km2 area around Atlin.
Currently only one road extends south of the O’Donnel River.
The Tlingits use an unregulated 4WD trail/road to access the IR5
reserve at Kuthai lake.
Not shown on the map is the Golden Bear Mine access road which
is located below the bottom of the map in the southern Taku/Inklin
watershed. That 150 km road served the former Golden Bear gold mine
from 1987 to 2002, providing access south to Telegraph Creek and
provincial Highway 37.
Figure 2 shows the road corridor options evaluated by Redfern in
the early stage of feasibility and environmental assessment permitting
(EA). Redfern consulting engineers and environmental consultants
evaluated the feasibility of these options at a preliminary stage
with respect to construction impediments, slope and terrain stability,
consultations with TRTFN and public, and early stage assessments
of environmental issues such as habitat values and sensitivities.
As a result some of the options were discarded early. Key among
these was the F-B segment which considered utilizing the main Taku
River valley. Construction feasibility and costs as well as highest
environmental parameter sensitivities quickly removed this corridor
from further consideration. The J-I, I-M and I-F segments were also
considered to be undesirable options. The first two were considered
by the TRTFN to potentially impact on their fishery and sockeye
spawning values at Kuthai Lake. The I-F segment was found to suffer
from geotechnical terrain instabilities and higher resulting costs
to protect sensitive fisheries values in Sloko and Goldbottom creeks
with higher risk of failure. Wildlife habitat values were also higher
in this option.
Option T-J utilizing the Warm Bay public road was opposed by many
residents of the community and also by the Ministry of Highways
due to the difficulty and cost of re-configuring the existing road
to meet safe truck hauling parameters. For this reason an alternate
route heading east of Atlin via Spruce Creek and Wilson Creek was
evaluated as a preferred option.
Figure 3 shows the area defined by the Project Committee for detailed
wildlife surveys and habitat assessment, primarily through the use
of Terrain Ecosystem Mapping (TEM). This 1600 km2 area was the focus
of a two-year program of TEM mapping and ground-truthing at 1:50,000
scale. Once completed, the data provided the basis for generation
of detailed maps rating habitats for both suitability and capability.
These were completed to provincial Resource Inventory Committee
(RIC) standards for 5 key species: caribou, sheep, mountain goat,
moose and grizzly bear.
The TEM map base covered all of the potential road corridor options
except for the Spruce Creek valley and the Warm Bay Road (considered
by the Committee to be already impacted by existing access).
Wildlife work included participation by local community representatives
and TRTFN in multi-season surveys, mapping crews, and progress reviews
in Project Committee meetings.
Figure 4: EA Fish and Fish Habitat
Assessment Scope (View
PDF 1,317 KB)
Figure 4 adds the areas of detailed fisheries surveys which were
mandated by the EA process. These surveys characterized the presence/absence
of anadromous and non-anadromous fish species, key habitats and
relative fisheries value of the various rivers, streams and creeks
along or traversing the potential road routes. The fisheries studies
were expanded in the mine area and also extended outside the wildlife
TEM mapping area to cover Spruce Creek and the end of the Warm Bay
Road.
This two-year multi-season survey program was conducted by qualified
independent fish biologists with assistance of local community participants,
including TRTFN, at various times and areas. Special attention was
focused on potential crossing areas and information gained by these
surveys was later utilized, where possible, to assist in selecting
crossing sites in areas of less-productive habitat.
Additional study information included DNA testing of DollyVarden/Bull
Trout hybrids to determine relative dominance and fish tissue sampling
for background metals content in selected sites – primarily
in the mine area.
During the later phases of the fisheries work Redfern initiated
field work by land surveying crews to define a preferred alignment
which selected a road route minimizing impacts to the various and
sometimes conflicting values presented by the overlain wildlife,
fisheries, community and aboriginal information and geotechnical
stability constraints – within the context of the regulated
road design parameters for concentrate hauling. Surveying crews
physically established a centre line alignment through the entire
proposed road route over a 2.5 year period. This included reconnaissance
terrain features and soils mapping, sufficient surveying of proposed
major crossings to complete conceptual plans and sections of crossing
designs, and preliminary road design including cut and fill volumes
and alignment plan and section layout. This information was used
to provide a well-qualified estimate of road construction and maintenance
costs for both the original Feasibility and Feasibility Update study.
The resulting alignment was advanced as the preferred alignment
through the final EA review process with supporting information
presented for all of the environmental baseline surveys.
The approved road alignment corridor post-EA was the subject of
a more detailed round of evaluation focused on finalizing the alignment
prior to granting of the Special Use Permit governing the construction
approval, operating requirements and closure terms for the access
road.
As outlined in Figure 5 more detailed work focused on completing
1:20,000 scale terrain stability field assessments, including mapping
of erosion potential and potential geotechnical hazards. This work
supplemented previous and new studies covering avalanche hazards,
flood and stream debris-flow hazards. More detailed assessment to
TSIL level C was conducted from the mine site to about kilometre
80, south of the Silver Salmon River. North of this point, in the
less precipitous highland terrain, the work was conducted at TSIL
level D.
One of the outcomes of this work was a requirement from the Ministry
of Forests to evaluate an amended alignment in the lower Nakonake
river valley to re-locate that portion of the alignment to the north
side, change the location of the Sloko River crossing in the east
and define a new crossing of the Nakonake river on the west to re-join
the original alignment.
Concurrently and pursuant to commitments contained in the Project
Approval Certificate, Redfern worked with the provincial government
to conduct 1:20,000 scale TEM mapping over selected portions of
the road corridor traversing or adjacent to high-quality grizzly
bear habitat. The purpose of this work was to refine the habitat
analysis at a finer scale (“patch habitat”) and determine
if small-scale road alignment changes were feasible to minimize
impacts or disturbance to grizzly bears.
More detailed fisheries work was conducted at selected sites and
crossings to refine crossing design parameters. A detailed assessment
of options to minimize disturbance of a TRTFN heritage trail was
undertaken from kilometres 65 to 80 immediately east of the Sloko
River.
Figure 6 displays the final road alignment after consideration
of all the completed studies and impact assessments. The SUP was
granted in 1999 with conditions and most of the conditions removed
by June of 2000 subject to submission of final engineering plans
and designs.
Amendments made to the original alignment of the EA are shown in
red or with text labels.
The SUP has once again become active as a result of the
new Project Approval Certificate granted by the provincial government.
Canadian Environmental Assessment Act (CEAA) supplemental screening
As a result of changes to the road alignment instituted during
the SUP permitting process, Fisheries and Oceans Canada (DFO)
determined that a supplemental process was required to amend the
original
CEAA screening authorization. In June 2002, DFO issued a letter
identifying individual issues for which new information was required.
Many of these issues were in areas where provincial agency responses
were required. As a result Redfern deferred a response until a
new decision on the project was made by the provincial authorities.
In early 2003 Redfern commenced a program of issue resolution and
entered into a joint contract with the province to hire a third
party consulting group (Axys Environmental) to compile all of the
wildlife information on the project gathered by both the company
and provincial studies.
In April 2004 Redfern submitted its response to issues identified
by Fisheries and Oceans Canada in order to finalize a screening
amendment approval under the Canadian Environmental Assessment
Act. DFO began a referral process and completed its draft screening
supplemental report in December of 2004. this document was released
for public comment on January 5, 2005 for a six week period ending
February 18, 2005. It is expected that the CEAA screening amendment
process will be completed
in
the spring
of 2005.
Operating Permits
The Tulsequah project will require a number of additional operating
permits before production can commence. Although many of these
are
routine, a few are key. These include the mine reclamation
permit, the Effluent Discharge and Waste Management Act permits,
the various Mines Act permits governing the design and construction
of the mine development, tailings impoundment and other project
infrastructure, and the CEAA screening amendment approvals.
Progress has been made on a number of fronts in these areas although
formal application for most is pending. Post 1998 certification
work established more detailed baseline work in the Shazah slough
and lower Shazah valley areas and Environmental Effects Monitoring
(EEM) baseline information was collected in this area and at sensitive
sites along the access road.
In the fall of 2003 and spring of 2004 Redfern worked with referral
agencies to finalize the protocols for satisfaction of the conditions
imposed in the Project Approval Certificate. These conditions relate
to completion of chronic
toxicity testing on proposed
effluent
discharge
material
and further
test
verification
of substrate sediments at the tailings impoundment site. Studies
and field programs were completed on these aspects in late May
and early June. Final reports are issued in July and August in
order to satisfy these requirements. In the late fall of 2004 Redfern
received written confirmation of satisfaction of the Certificate
conditions.
|